Civil Engineering UK | London | Sussex | Surrey | Kent | Hampshire

Wycombe Retail Park: Building a Drainage System Ready for the Next Downpour

The Shore Group is delivering a comprehensive car park drainage and resurfacing project at Wycombe Retail Park in High Wycombe, replacing an outdated permeable paving system with upgraded drainage infrastructure designed to better manage heavy rainfall.

2 Min

AT A GLANCE

Location

High Wycombe, Buckinghamshire

High Wycombe, Buckinghamshire

Start Date

Services
Civils
Groundworks
Drainage
Car Park
High Wycombe
Retail
Infrastructure
Services
Civils
Groundworks
Drainage
Car Park
High Wycombe
Retail
Infrastructure

Wycombe Retail Park: A drainage solution built for heavy rainfall


The Challenge

Following heavy rainfall, water was pooling across the parking bays at Wycombe Retail Park. The existing permeable paving system was no longer coping with the demands placed on it, this presented a clear need to upgrade the car park's drainage infrastructure.

The Shore Group was appointed to deliver the civils and groundworks package, replacing the outdated system and upgrading the underlying construction.


The Works

The project involved excavating to formation, 480mm below the existing road construction, before installing a specified membrane across the base

The new drainage infrastructure included manholes, catch pits and diffusers, with the system designed to filter water through the stone and channel it away from the car park surface.

The drainage network was also connected into the main storm drainage system, providing a defined route for surface water.

The wider works included new block paving and speed bumps, completing the car park upgrade.


Phased Delivery in a Live Retail Environment

A key consideration was maintaining access to Wycombe Retail Park throughout the works.

The project was delivered across four phases over a 14-week programme, allowing construction activities to be sequenced while the car park remained open and retail operations continued.

This approach required careful planning and coordination to deliver the works within a busy operational environment.


The Result

The completed project has delivered a new block-paved car park surface and upgraded drainage infrastructure at Wycombe Retail Park.

By addressing the existing drainage arrangement and renewing the underlying construction, The Shore Group has delivered a comprehensive civils and groundworks solution for the retail park.

The project demonstrates our approach to practical engineering, phased delivery and the coordination required to complete infrastructure works in live environments.


Discuss Your Next Project

Have a civils, drainage or groundworks project that needs a practical, reliable approach?



Upgraded car park drainage and new block paving with speed bumps at Wycombe Retail Park, delivered in four phases over a 14-week programme while keeping the retail park open.

A large construction site with workers and heavy machinery is surrounded by scaffolding and a partially constructed building in an urban area.

GET IN TOUCH

Ready to Build What’s Next?

Speak with our team to explore your project needs and how we can help deliver it — efficiently, safely, and at scale.

The Shore Group
Rob Green

Director - Civils

A large construction site with workers and heavy machinery is surrounded by scaffolding and a partially constructed building in an urban area.

GET IN TOUCH

Ready to Build What’s Next?

Speak with our team to explore your project needs and how we can help deliver it — efficiently, safely, and at scale.

The Shore Group
Rob Green

Director - Civils

A large construction site with workers and heavy machinery is surrounded by scaffolding and a partially constructed building in an urban area.

GET IN TOUCH

Ready to Build What’s Next?

Speak with our team to explore your project needs and how we can help deliver it — efficiently, safely, and at scale.

The Shore Group
Rob Green

Director - Civils

CASE STUDIES

Project highlights.