Hemel Hempstead 4 Data Centre, Hertfordshire
M&E data centre solutions in Hertfordshire.
1 Nov 2021
Client
Location
Hertfordshire
PROJECT VALUE
£1.5M
Sector
DATA.
Start Date
Aug 2025
1-year data centre programme of M&E fitout working in partnership for high-profile end client at data centre site. The Shore Group managed the delivery of a core team of 15 engineers on-site throughout the programme ramping capacity up to a peak of an additional 50 engineers to support peak periods.
Fixed-price delivery responsibility included a fully-scoped works package, H&S requirements and risk management for the programme.
Scope of Services:
Fixed-priced works package
Cooling system
Emergency cooling system
FAP framework
Data containment spine works
CCTV system
BMS panelling
Transformer movements
Cage installation to all RMUs
Main hall lighting
H&S management and reporting