Take over of Medical Centre Construction Programme

The Shore Group took over and completed the remaining works at St Peter’s Medical Centre, Brighton following the insolvency of the previous contractor, ensuring minimal disruption to project delivery and programme.

3 mins

Modern brick apartment building with contemporary architecture, large vertical windows, and blue tiled accents on a quiet urban street

AT A GLANCE

Location

Brighton

Brighton

PROJECT VALUE

£1.2m

£1.2m

Start Date

Services
Property Works
Contractor Packages
Fit Out
Services
Property Works
Contractor Packages
Fit Out

The Shore Group seamlessly took over and completed the remaining works at St Peter’s Medical Centre, Brighton following the insolvency of the previous contractor, ensuring minimal disruption to project delivery and programme.


PROJECT SCOPE

The new Medical Centre replaces an existing Medical Centre for our client Medical Centre Developments Limited. Situated in a city centre location and serving a population with high levels of need, the centre supports a high-demand for mental health and substance misuse services.

To ensure continuity of care provision for the local community, the existing medical centre was required to remain open throughout the project.

Functioning as a GP medical practice, centre for the NHS Foundation Trust and with space for a proposed pharmacy, the new medical centre has four floors from ground through to 3rd floor.

The Shore Group became Main Contractor in November 2023, with the site in enforced closure following insolvency. The project supply chain was significantly impacted by financial loss from the original contractor requiring proactive management and communication.


PROACTIVE SOLUTIONS

The Shore Group became Main Contractor in November 2023, with the site in enforced closure following insolvency. The project supply chain was significantly impacted by financial loss from the original contractor requiring proactive management and communication.

By carefully coordinating mechanical and electrical installations, carpentry, floor finishes, and other internal works, they ensured a adhered to a tight programme, deliver high-quality results.

The phased construction approach allowed the existing Medical Centre to remain operational throughout the project, minimising disruption to services and maintaining continuous care for the community.

DELIVERY BENEFITS

EXPERT PROJECT MANAGEMENT

Smooth transition and completion of the project following contractor insolvency

PHASED IMPLEMENTATION

Uninterrupted healthcare services for the local population with phased programme

SUPPLY CHAIN ENGAGEMENT

Continuity of contractor works package delivery working with client and supply chain

COMMUNITY BENEFITS

The Shore Group worked with local tradesmen and sub-contractors including carpenters, electricians, plumbers, labourers, painters and decorators to maximse the economic benefit for the local community. This approach aligns with our brand ideal and social value programme.

A large construction site with workers and heavy machinery is surrounded by scaffolding and a partially constructed building in an urban area.

GET IN TOUCH

Ready to Build What’s Next?

Speak with our team to explore your project needs and how we can help deliver it — efficiently, safely, and at scale.

Ross Donnelly
Ross Donnelly

Head of Group Business Development

A large construction site with workers and heavy machinery is surrounded by scaffolding and a partially constructed building in an urban area.

GET IN TOUCH

Ready to Build What’s Next?

Speak with our team to explore your project needs and how we can help deliver it — efficiently, safely, and at scale.

Ross Donnelly
Ross Donnelly

Head of Group Business Development

CASE STUDIES

Project highlights.